Some necessary improvements and renovations to the current high school building began this summer:

  • The roof over several classrooms, the auxiliary gym and the main gym, have been replace and other section have been repaired
  • Installation of upgraded and new cameras has begun in both the interior and exterior areas of the building

Many of the renovations for this project are currently in the design/planning phase, including:

  • Upgrades to the heating systems, office area, corridors, restrooms, locker rooms, and classrooms
  • Demolition of the old wooden portion of the building, creating a new, secure entrance for the building

Bid date: Aiming November

Construction Reports